Importation of new rails |
Unloading on the quays of the port of Douala |
OFFICIAL CEREMONY OF LAUNCHING OF THE WORK OF RENEWAL OF THE WAY BETWEEN BELABO AND KA'A" ON SEPTEMBER 11, 2004 |
|
|
This work requires an important technicality. |
|
|
Semi-mechanized raking of the way |
Pose of the rails with the carriage platelayers |
|
|
Fixing of the new way |
Heavy mechanical stuffing |
|
|
Control rail by ultrasound |
Check geometrical parameters of the way
by Rail-Car M-462 |
Camrail oversees the delegated works for investment programmes and renewals contracted by the State.
To provide an example, between 2007 and 2014, the State's priority investment plan implemented by Camrail saw track renewal in the following sections of the line :
DIBAMBA – MAKONDO (66 km)
BATCHENGA – KAA (126 km)
|